6 Apr 2022
1. ) Kok Sue Lynn 2. ) Julia Soh Ming Yee 3. ) Lai Wai Hong 4. ) Yeap Li Ching 5. ) Yeap Dah Shen 6. ) Lim Liwu 7. ) Priscilla Cheah Siow Wen Mayfair Ventures Sdn Bhd
- Citation
- BA-22NCvC-284-07/2021 (Mahkamah Tinggi)
- Court
- High Court
- Case number
- BA-22NCvC-284-07/2021 (Mahkamah Tinggi)
Plaintiffs had locus standi under clause 8 of the statutory Schedule H SPA; Schedule H fixes a 36-month completion period which cannot validly be varied to 42 months absent valid, communicated approval which was not produced; LAD is payable from the date of payment of the booking fee; defendant failed to establish any triable issue or valid settlement precluding the LAD claims, and therefore summary judgment for the plaintiffs was proper.