24 Jun 2022
WA-22NCVC-120-02/2020 (Mahkamah Tinggi)
- Citation
- WA-22NCVC-120-02/2020 (Mahkamah Tinggi)
- Court
- High Court
- Case number
- WA-22NCVC-120-02/2020 (Mahkamah Tinggi)
Where the contractual document and the date of handing over vacant possession were undisputed and the sole dispute concerned the legal question of the applicable completion period, the court properly exercised its discretion under Orders 14A, 33 and 34 to determine the legal issue without a full trial and allowed the Plaintiff's application.