YAN AI HONG SKT CONSTRUCTION SDN. BHD.
- Citation
- DA-A52NCvC-29-07/2023 (Mahkamah Sesyen)
- Court
- Sessions Court
- Case number
- DA-A52NCvC-29-07/2023 (Mahkamah Sesyen)
Because the sale was a statutory Schedule H contract, the developer was immediately liable for liquidated damages under Clauses 25 and 27 once completion dates passed; the defendant's asserted cause of delay (plaintiff's renovations) failed because defendant consented and withheld material witness evidence and did not seek statutory extension; therefore plaintiff entitled to RM225,067.39 and defendant's counterclaims fail.