1 Apr 2022
WA-22NCC-347-06/2019 (Mahkamah Tinggi)
- Citation
- WA-22NCC-347-06/2019 (Mahkamah Tinggi)
- Court
- High Court
- Case number
- WA-22NCC-347-06/2019 (Mahkamah Tinggi)
Court found a binding contract existed governed by the tender documents and KFN002/2018; FIAM terms did not apply and the alleged 21 December 2017 agreement and its timetable were not authentic or communicated to the plaintiff; delivery period extended to 30 September 2018 under the akuan, defendant accepted deliveries without protest so time became at large and defendant acquiesced to any delays; defendant therefore not entitled to late delivery penalty and plaintiff entitled to principal claim of RM4,138,780.60 but not to FIAM late payment interest or SOGA interest.