24 Mar 2025
1. ) CHOW CHEE WAH 2. ) MOHD DHIYAUDDIN ASSIDDIQ BIN MOHD ZAID 3. ) WILLIAM TEH YEW HOUNG 4. ) DENISE TEOH SHYN YONG XTREME MERIDIAN SDN BHD
- Citation
- WA-B52NCvC-244-06/2022 (Mahkamah Sesyen)
- Court
- Sessions Court
- Case number
- WA-B52NCvC-244-06/2022 (Mahkamah Sesyen)
The court held that the 48-month delivery period stated in the sale agreements is valid because the extension was lawfully obtained before the Ang Ming Lee decision and Obata-Ambak treats Ang Ming Lee as prospective; plaintiffs are nevertheless entitled to LAD only for delays beyond the valid 48-month period, with LAD calculated from the date of payment of the deposit/booking fee using the purchase price in the Sale and Purchase Agreement; interest at 5% per annum from filing until full payment and costs ordered as below.