29 Jul 2022
Muhammad Muaz bin Abdul Malek Modal Ehsan Sdn Bhd
- Citation
- BA-24NCvC-408-03/2022 (Mahkamah Tinggi)
- Court
- High Court
- Case number
- BA-24NCvC-408-03/2022 (Mahkamah Tinggi)
Affidavit evidence and contemporaneous documents established delay and liability on the balance of probabilities at the upper end of the scale; therefore r.3(c) of O.22A is satisfied. Because this is an interlocutory application and quantum can be adjusted at trial, the court adopted the defendant's own most favourable LAD computation scenario for the interim stage and awarded RM510,964.96 as interim payment (RM425,804.15 for vacant possession and RM85,160.83 for common facilities).