1 Oct 2020
APEX COMMUNICATIONS SDN BHD AGROW BUILDERS SDN BHD
- Citation
- BA-12BNCvC-36-03/2020 (Mahkamah Tinggi)
- Court
- High Court
- Case number
- BA-12BNCvC-36-03/2020 (Mahkamah Tinggi)
Retention money of RM63,117.00 ordered released; idling costs allowable only for material shortage, stop‑work instructions and late issuance of RFI as falling within clause 27.2; depletion of pile‑points and surveyor late pegging were not proved or not within recoverable events and awards for those items were set aside; RM8,700/day accepted as reasonable quantum rate for idling and applied for awarded days; total award reduced to RM137,067.00 and appeal allowed in part.