13 Sept 2024
MAHKOTA TECHNOLOGIES SDN BHD AFRIMA CONSULTING ENGINEER SDN BHD
- Citation
- BA-22C-53-12/2020 (Mahkamah Tinggi)
- Court
- High Court
- Case number
- BA-22C-53-12/2020 (Mahkamah Tinggi)
The Plaintiff failed to prove on the balance of probabilities that the Defendant breached the LOA in respect of PMC or erection works and failed to establish the specific works and costs for backcharges; evidence established that delay was attributable to defective materials supplied by the Plaintiff (via Zelleco) and not Defendant; non‑pleaded reliance on the RFP could not be admitted; no evidence of unresolved defects at termination; therefore Plaintiff’s claims dismissed and Defendant’s counterclaims for proved items allowed, with net award.