Final re-measurement and revaluation performed by a qualified quantity surveyor using as-built drawings verified by the consultant civil engineer were accepted as compliant with contract; specific disputed variation valuations and backcharges were resolved on evidence and contractual valuation rules; First Defendant failed to substantiate prolongation/loss claims and did not comply with contractual notice/evidence requirements; Second Defendant was entitled to direct payment under sub-contract clauses and the parties' undertaking and alternatively under s.71; accordingly judgment for Plaintif…