4 Jun 2025
1. ) KOH THUANG KOK 2. ) TAN CHEN FUI ERA UNIVERSE DEVELOPMENT SDN BHD
- Citation
- JA-A52NCvC-339-11/2024 (Mahkamah Sesyen)
- Court
- Sessions Court
- Case number
- JA-A52NCvC-339-11/2024 (Mahkamah Sesyen)
Court held defendant had no meritorious defence: COVID-19 Act exclusions did not apply to the commercial shop-office SPA; SPA became unconditional on 16.11.2017 when Supplemental Agreement classified the lot as non‑Bumiputera, making the developer's obligation to deliver vacant possession due on 16.11.2020; actual delay of 605 days occurred and agreed liquidated damages pursuant to SPA are enforceable without proof of actual loss; summary judgment was therefore appropriate and awarded with amended LAD of RM145,664.10 plus interest and costs.