18 Oct 2022
1. ) MOHD AKMAL BIN AZMI 2. ) HAIFARIZA BINTI ARZEMI MERCHANT SYNERGY SDN BHD
- Citation
- BB-A72NCvC-472-08/2021 (Mahkamah Majistret)
- Court
- Magistrates' Court
- Case number
- BB-A72NCvC-472-08/2021 (Mahkamah Majistret)
Defendant was a contractor not a housing developer; clause 5 required vacant possession to include utilities ready for connection and that condition was not satisfied within 24 months because external infrastructure was the developer's responsibility; plaintiffs failed to prove defendant was a developer or that defendant alone was liable for external utility works, and plaintiffs were responsible for ensuring the developer performed; therefore defendant not liable for the liquidated damages claim and claim is dismissed.