11 Sept 2025
TOSHIBA Elevator (Malaysia) Sdn Bhd TANJUNG TERAS SDN BHD
- Citation
- WA-A52NCvC-33-01/2022 (Mahkamah Sesyen)
- Court
- Sessions Court
- Case number
- WA-A52NCvC-33-01/2022 (Mahkamah Sesyen)
On the balance of probabilities the court found Plaintiff completed the contracted works and proved variation works of RM53,432.00; Defendant failed to prove any agreement by Plaintiff to reduce the contract price and Defendant's 2018 acknowledgment revived the limitation period; accordingly Plaintiff was entitled to the unpaid balance of RM178,963.70 and the claim was not time-barred.