15 Sept 2021
Syarikat Pembinaan Anggerik Sdn Bhd Malaysia Airports Holdings Berhad
- Citation
- BA-22C-23-04/2017 (Mahkamah Tinggi)
- Court
- High Court
- Case number
- BA-22C-23-04/2017 (Mahkamah Tinggi)
On the balance of probabilities the court accepted the defendant consultant’s draft Final Account valuations generally but adjusted specific errors shown by plaintiff evidence; allowed net recoveries for works done of RM2,036,521.50 (Package 1) and RM8,642,914.73 (Package 2) but set off LAD of RM750,000 (ADW) leaving Package 1 net RM1,286,521.50; dismissed acceleration and prolongation claims for failure to prove causation and for failing to comply with contractual notice/estoppel requirements under clause 44; applied the prevention principle to dismiss defendant’s LAD claim for CUB and limit…