22 Aug 2025
YENG YING SDN. BHD. LLC INFRA SDN BHD
- Citation
- WA-22C-32-05/2022 (Mahkamah Tinggi)
- Court
- High Court
- Case number
- WA-22C-32-05/2022 (Mahkamah Tinggi)
On the evidence the Court found the Plaintiff did not establish a mutual agreement to hand over incomplete works (only Location 13 properly handed over); Plaintiff failed to prove any valid contractual variation permitting partial completion; Plaintiff breached the LOA by failing to complete works and not applying for EOT; Defendant was entitled to complete works and to set-off/back charges supported by documentary evidence and to recover contractually stipulated LADs. Consequently Plaintiff's claim is dismissed and Defendant's counterclaims and set-offs are allowed in the specified sums, wit…