SIN KEAN BOON METAL INDUTRIES SDN BHD v TRIKKON CONSTRUCTION SDN BHD
- Citation
- SIN KEAN BOON METAL INDUTRIES SDN BHD v TRIKKON CONSTRUCTION SDN BHD
- Court
- Malaysian court
Five weeks from appearance (two weeks after defence) was not inordinate delay and the affidavit served more than four clear days before the return date complied with O.14 r.2; however, disputed issues as to whether claimed shortfall related to additional works outside the subcontract and whether architect's certificates were conclusive raised triable issues, so summary judgment was inappropriate and the interlocutory grant of leave to sign final judgment was set aside.