10 Jan 2023
LYCONNA CORPORATION SDN BHD DESTINI ONE DEVELOPMENT SDN BHD
- Citation
- WA-A74-2932-10/2022 (Mahkamah Majistret)
- Court
- Magistrates' Court
- Case number
- WA-A74-2932-10/2022 (Mahkamah Majistret)
The court held the architect's purported extension (31.1.2019–31.3.2019) was issued for reasons outside the enumerated causes in Clause 18.1 and under the building contract clause to which the Plaintiff was not privy; therefore the extension was outside the scope of Clause 18.1, manifestly erroneous and not binding. No valid extension covered 16.4.2018–30.1.2019. Under Clause 19.2 vacant possession was deemed taken on 5.4.2019. Plaintiff proved delay on the balance of probabilities and was entitled to RM54,175.15 liquidated damages, interest at 5% from judgment until full settlement, and cost…