20 Aug 2025
1. ) SMOOTH ACHIEVEMENT SDN BHD 2. ) HYPER INDUSTRIAL AUTOMOTIVE SDN BHD 3. ) KUA SWEE KIAT 4. ) KUA SWEE KEONG 5. ) SWISSMA BUILDING TECHNOLOGIES SDN BHD 6. ) PLY-MART SDN BHD 7. ) CHUA TONG HIN HARDWARE SDN. BHD. 8. ) RECTECH RESOURCES SD
- Citation
- B-02(NCvC)(W)-1020-06/2023 (Mahkamah Rayuan)
- Court
- NCvC
- Case number
- B-02(NCvC)(W)-1020-06/2023 (Mahkamah Rayuan)
Court construed Clauses 5 and 11 of the bespoke SPA to mean vacant possession is given upon completion of civil works and civil infrastructure works serving the project; M&E works (energisation, pump equipment installation) are to be carried out subsequently by utility providers upon purchasers' applications and are not preconditions to contractual delivery of vacant possession. The stage completion certificates issued on 7 and 30 September 2015 were valid. Liquidated damages under clause 5.3 are assessed by reference to contractual delivery dates and actual delivery date; s.75 Contracts Act…