2 Dec 2024
1. ) LEE MENG HUNG 2. ) TAN LEA HUH ERA UNIVERSE DEVELOPMENT SDN BHD
- Citation
- JA-A52NCvC-185-06/2024 (Mahkamah Sesyen)
- Court
- Sessions Court
- Case number
- JA-A52NCvC-185-06/2024 (Mahkamah Sesyen)
The court held the Act 829 exclusion did not apply because the subject property is commercial and not a housing accommodation under the prescribed SPA schedules; the 36-month delivery period ran from the developer's written notification of non-Bumiputera status dated 30.6.2017, therefore delay is computed from 30.6.2020 to 14.6.2022; defendant had no meritorious defence and plaintiffs were entitled to liquidated damages of RM136,988.90; summary judgment under Order 14 KKM 2012 was granted with costs RM3,000.00.