19 Feb 2024
1. ) AHAD JOHARI BIN DAWOD 2. ) MUSTAFFA BIN IBRAHIM BINA SEMPURNA (M) SDN BHD
- Citation
- AA-A72NCvC-530-12/2021 (Mahkamah Majistret)
- Court
- Magistrates' Court
- Case number
- AA-A72NCvC-530-12/2021 (Mahkamah Majistret)
Court held on the balance of probabilities that delivery was delayed; clause 10.1 must be read in context and, because plaintiff paid cash and defendant commenced works without valid justification or notice of delay, the 24-month period runs from the date of the building agreement (11.09.2013) not from plan approval; liquidated damages therefore accrued upon actual delivery (15.01.2019) and the claim was not time‑barred, entitling plaintiff to the contractual LAD calculated at RM41,862.58.