15 Aug 2025
REALCO PROPERTIES SDN BHD JT BINAJATI SDN. BHD
- Citation
- CA-B52C-3-04/2023 (Mahkamah Sesyen)
- Court
- Sessions Court
- Case number
- CA-B52C-3-04/2023 (Mahkamah Sesyen)
On the balance of probabilities the Plaintif failed to discharge the burden to prove defects and utility‑pipe interference; Plaintif breached contractual obligations by failing to appoint a site supervisor and by delaying/withholding payments, thus Defendan validly terminated for fundamental breach and is entitled to outstanding progress sums (RM101,229.53), retention (RM6,982.01), interest at 5% and costs; Plaintif's claims (including LAD and claimed RM333,742) are dismissed.