24 Oct 2023
RAU PAENGA LIMITED v CPB CONTRACTORS PTY LIMITED [2023] NZHC 2974
- Citation
- [2023] NZHC 2974
- Court
- High Court
The Court granted interim relief restraining CPB from requiring the Engineer to suspend or terminate under cl 14.3.3 because RPL demonstrated a reasonable possibility of success on the merits that CPB's default notices were defective and contestable, that suspension/termination would cause harm not adequately reparable by damages (including loss of personnel, warranties, subcontractor continuity and third-party interests), and the balance of harm favored preserving the status quo to allow the contractual dispute resolution (Engineer decision then arbitration) to proceed.