13 Dec 2019
FOCUS CONSTRUCTION INTERIORS LTD v SPACEWORKS DESIGN GROUP LTD [2019] NZHC 3296
- Citation
- [2019] NZHC 3296
- Court
- High Court
Court awarded costs to defendants: applied band 2B generally but band C for preparation of briefs and trial preparation, and allowed a 50% uplift of costs items from preparation of briefs onward (post-April 2019 Calderbank offer) because the plaintiff unreasonably failed to accept the April 2019 offer; resulting costs $85,409 plus disbursements $14,358, payable by the plaintiff to the defendants.