12 Jun 2017
RESOURCES SERVICES LTD v AMR NICKEL LTD [2017] NZHC 1267
- Citation
- [2017] NZHC 1267
- Court
- High Court
Because the defendants failed in their strike out and summary judgment bids but partially succeeded on security for costs, and because the defendant-initiated summary judgment was essentially the same as the strike out application and did not produce Philpott-type benefits, the court fixed costs now: awarding costs to the plaintiff on the strike out/summary judgment components with a 30% reduction under r14.7(g) to reflect the defendants' success on security for costs.