26 Jul 2021
COLMAT CONSTRUCTION AND ENGINEERING CO LTD v. MINMETALS CONDO (HONG KONG) ENGINEERING CO LTD
- Citation
- [2021] HKCFI 2184
- Court
- Court of First Instance
- Case number
- HCCT36/2018
The Contract incorporated the drawings and technical specifications relevant to the Plaintiff's subcontract works but did not incorporate the main contract's or MC's full General or Special Conditions; the Contract is a remeasurement contract based on flat area so unit rates in the schedules govern valuation of variations (not weight-based measurement); many of the Plaintiff's variation claims fail for liability or for lack of substantiation; most contra charges claimed by the Defendant fail for lack of sufficient evidence though specified discrete amounts were allowed where supported by evid…