WING LOK CONSTRUCTION & ENGINEERING CO LTD v. TECHOY CONSTRUCTION CO LTD
- Citation
- [2025] HKCFI 5546
- Court
- Court of First Instance
- Case number
- HCCT2/2023
Wing Lok failed to discharge the burden of proof on the quantum meruit claim for WI74 because it produced no expert evidence to justify applying the subcontract rate; the penalties/fines were enforceable as proportionate protections of Techoyʹs legitimate interests; rectification costs were necessary and recoverable contra‑charges; netting of claims and counterclaims resulted in Wing Lok owing Techoy HK$377,005.58 with interest and costs.