Menteri Besar Selangor (Pemerbadanan) Pentadbir Tanah Daerah Gombak PENCELAH MALAYSIA RAIL LINK SDN BHD
- Citation
- BA-15-275-10/2024 (Mahkamah Tinggi)
- Court
- High Court
- Case number
- BA-15-275-10/2024 (Mahkamah Tinggi)
Court increased the land value from RM95.00/sqm to RM105.00/sqm and awarded additional compensation of RM90,010.00 (land value) and RM315,459.90 (pecah pisah) with late payment interest at 5% per annum from date of Form K until full settlement. Court dismissed applicants' further claims for additional compensation for injurious affection and incidental costs because applicants failed to prove diminution or disruption to the remainder land to the requisite standard.