14 May 2023
ASTINAS CONSTRUCTION & DEVELOPMENT SDN BHD GINMIT TRADING SDN BHD
- Citation
- JA-12BNCvC-11-06/2022 (Mahkamah Tinggi)
- Court
- High Court
- Case number
- JA-12BNCvC-11-06/2022 (Mahkamah Tinggi)
Clause 24 is clear: the 24-month delivery period is measured from the date of approval of the proposed building plan by the local authority (MBJB). The Sessions Court erred in applying estoppel and illegality to reframe the contractual timeline; commencing works without approval did not create an underlying assumption sufficient for estoppel nor a nexus rendering the defence unavailable. Accordingly the defendant delivered within the contractual period and the respondent's LAD claim fails.