13 Jan 2026
Airnovate Sales & Services Sdn Bhd Golden Age Development Sdn Bhd
- Citation
- KF-A52NCvC-13-09/2025 (Mahkamah Sesyen)
- Court
- Sessions Court
- Case number
- KF-A52NCvC-13-09/2025 (Mahkamah Sesyen)
Defendant bore responsibility for the delay because initial and material delays were within Defendant's control; the 14-day period after the architect's notice is part of the delay by operation of clause 21(2); Defendant had no meritorious defence, therefore summary judgment was proper and Plaintiff entitled to liquidated damages of RM120,246.58 and interest as claimed.