6 Jan 2026
SEMARAK NALURI SDN. BHD. 1. ) SPORTS TECH PRO SDN. BHD. 2. ) THANURAJ A/L IVAYU 3. ) SINAR BINA MAJU (M) SDN. BHD.
- Citation
- BA-22C-33-10/2022 (Mahkamah Tinggi)
- Court
- High Court
- Case number
- BA-22C-33-10/2022 (Mahkamah Tinggi)
Plaintiff's claims were dismissed because the Court found the non-completion and delays were attributable principally to the Plaintiff's failures (notably non-payment and conduct granting/promising EOT), the Plaintiff was estopped from imposing LAD for the period covered by EOT, suspension of works by the 1st Defendant was justified, the 1st Defendant later obtained FIFA certification, and the 3rd Defendant was entitled to its unpaid progress claims (counterclaim allowed in part).