XXXX Fairview International School Nusajaya Sdn Bhd
- Citation
- W-02(NCvC)(W)-18-01/2022 (Mahkamah Rayuan)
- Court
- NCvC
- Case number
- W-02(NCvC)(W)-18-01/2022 (Mahkamah Rayuan)
The LOA fixed a six-month completion to 28 Feb 2015 and contained an express LAD of RM10,000/day which, under the LOA's precedence clause, overrides the GCS cap; the defendant did not validly apply for extension of time under the PAM procedure and unlawfully suspended and failed to complete the works, so LAD ran from 1 Mar 2015 to JKKP certification on 2 Jun 2015 (94 days) equating to RM940,000; plaintiff was entitled to recover third-party rectification costs because defendant failed to deliver works fit for purpose and no valid payment certificates supported defendant's counterclaim, hence…