30 Aug 2021
RC ASIA ENGINEERING SDN BHD LION PACIFIC SDN BHD
- Citation
- WA-22C-52-06/2019 (Mahkamah Tinggi)
- Court
- High Court
- Case number
- WA-22C-52-06/2019 (Mahkamah Tinggi)
The court found the Defendant caused material prevention (late handovers, insufficient supplies, design changes) making time for completion at large; Plaintiff was entitled to complete within reasonable time (held 30 April 2017) and to limited prolongation costs for the idling period (3–14 January 2017). Defendant's liquidated damages claim was barred; Defendant entitled to assessed set-off for backcharges (RM200,000). Net judgment for Plaintiff RM557,673.52 with interest and costs.