25 Oct 2023
EXCEL M&E SDN BHD MUJUR SEPAKAT SDN BHD
- Citation
- CA-22C-1-08/2018 (Mahkamah Tinggi)
- Court
- High Court
- Case number
- CA-22C-1-08/2018 (Mahkamah Tinggi)
The court found on the balance of probabilities that the plaintiff completed the contracted works as evidenced by Bomba inspections and CFO/CCC issuance, that variation works were instructed and completed, and that prolongation costs arose from defendant-caused hindrance; the defendant failed to adduce contrary documentary evidence or show defects, therefore plaintiff is entitled to the unpaid lump sum, variations, and prolongation costs; defendant's counterclaim is dismissed.