25 Jun 2024
Bolt Industries Sdn Bhd Itramas Re Services Sdn Bhd
- Citation
- BA-12BC-3-02/2024 (Mahkamah Tinggi)
- Court
- High Court
- Case number
- BA-12BC-3-02/2024 (Mahkamah Tinggi)
Court found Defendant proved entitlement to deduct RM42,930 for the 53 damaged PV modules (admitted by Plaintiff) but failed to prove entitlement to deduct RM54,351.12 as liquidated damages and RM18,800 as third‑party completion costs; delay was attributable to Defendant so LAD was not payable; Defendant had not shown actual payment to third party or that Plaintiff had been paid for those missing works; hence Plaintiff entitled to recover RM73,151.12 (RM54,351.12 + RM18,800.00) with 5% interest from 20.7.2019; costs to be borne by parties themselves.