12 May 2022
1. ) RAJOO A/L PARIASAMY 2. ) NOEL YEO LIP SIN 3. ) ANDREW TAN MEN XIAN 4. ) TAN TEOW ANN 5. ) TEO HOCK CHOON 6. ) TEO WEI ZHEN, RYAN 7. ) YONG KWA SIEW PREMA BONANZA SDN. BHD. PIHAK KETIGA DICADANGKAN 1. ) Kerajaan Malaysia 2. ) MENTERI PE
- Citation
- WA-22NCvC-674-10/2021 (Mahkamah Tinggi)
- Court
- High Court
- Case number
- WA-22NCvC-674-10/2021 (Mahkamah Tinggi)
The statutory 36-month completion period applies and is calculated from payment of booking fees; any purported extension to 54 months is invalid; discounts cannot be deducted for calculating the late delivery penalty and are not refundable as they formed part of the contractual offer, therefore the defendant has no defence and its counterclaim fails.