15 Feb 2017
CHUN WO BUILDING CONSTRUCTION LTD v. METTA RESOURCES LTD
- Citation
- CHUN WO BUILDING CONSTRUCTION LTD v. METTA RESOURCES LTD
- Court
- Court of First Instance
- Case number
- HCCT29/2013
VO claims amended on 16 December 2015 attract pre-judgment interest from that date; the design input award was insufficiently pleaded/quantified and attracts no pre-judgment interest; IPC 28 and 29 attract pre-judgment interest from their contractual due dates because the court will not look behind certificates given the breakdown of contractual machinery; diminution as set-off does not attract interest; Chun Wo is awarded 70% of its costs (to be taxed if not agreed), no costs order made on Metta's Counterclaim, and a certificate for four counsel is granted.