18 Nov 2021
FRUIT DESIGN AND BUILD LTD v. LEUNG KWOK PONG ALSO KNOWN AS ADAM LEUNG
- Citation
- [2021] HKCFI 3391
- Court
- Court of First Instance
- Case number
- HCA334/2020
The court held that the plaintiff's 2019 contractual claim for unpaid progress payments under IPA Nos 8–16 is a liquidated demand because the Progress Payment Clause conferred an ascertainable interim valuation mechanism; the plaintiff's post-judgment application to amend to add quantum meruit was disallowed as not exceptional and requiring writ amendment; the 2019 final judgment was irregular as entered for amounts exceeding contractual entitlement and was therefore varied down to HK$3,514,686 while the 2020 final judgment (which duplicated claims and contained unliquidated elements) was set…