17 Dec 2025
HUNG LEE DECORATION ENGINEERING LTD v. DAVID DECORATION LTD
- Citation
- [2025] HKDC 2002
- Court
- District Court
- Case number
- DCCJ3226/2021
Clause 5 must be read with the schedule: the agreement is lump sum only to the extent of the specified quantities; excess quantities are payable at schedule unit rates; PQS approval is not a general condition precedent to payment where parties agree the price or a schedule unit rate applies; where no price is agreed an implied term requires payment of a reasonable sum; Payment Declarations executed by the plaintiff were partial receipts and did not bar further claims; the defendant failed to plead or prove set‑offs; the Jessville clause did not create a pay‑when‑paid condition precedent.