20 Apr 2015
A I D LTD v. NANYANG BROTHERS TOBACCO CO LTD
- Citation
- A I D LTD v. NANYANG BROTHERS TOBACCO CO LTD
- Court
- District Court
- Case number
- DCCJ876/2014
Court found defendant caused/prevented delay to Phase 1 by late confirmation of sanitary fittings and shop drawings and by conduct causing rescheduling so time for Phase 1 was rendered at large and the 35 day delay was reasonable; although contract construed to require Phase 2 to commence immediately after Phase 1, the parties agreed (and defendant failed to rebut) commencement on 16 February 2013 so Phase 2 completed within 45 days; defendant proved some defects but only nominal damages HKD1,000 were provable; judgment entered for plaintiff for HKD501,060 (DCCJ 1559/2013) and HKD118,300 (DCC…